Set up a Timeline and Schedule for Data Centers in the Asset Module

Overview: data center schedule and timeline


Asset module scheduling lets you assign start and end dates to checklists across levels, import dates from Excel, and manage the plan in a Gantt timeline, which is used for Level 2-5 data center test sequences.


Assets and checklists must already exist before you plan dates.


  • Your role must be Manager or higher.
  • You can find the menu at Assets - date columns, or menu - Gantt Timeline.
  • This changes checklist dates, Gantt bars, and dependency links. Folder-level date changes affect all underlying checklists.


Only users with the project role Manager or higher can plan and edit commissioning plans.


How to schedule data center checklists


Video guide



Plan checklists directly in the asset view

  1. Go to your project and open Assets.
  2. Select an asset, for example ATS.
  3. In the Start date and End date columns, select a date in the grey row for a level, for example Level 3.
  4. Confirm CxPlanner assigns dates to all underlying checklists.


Plan one checklist at a time

  1. Click the start date for a specific checklist.
  2. Select a date.
  3. Repeat for the end date.


Import plan from Excel

  1. Go to Asset Overview and click Options.
  2. Select Import.
  3. Upload your Excel file with dates.


Use the Gantt timeline

  1. Open the menu and select Gantt Timeline.
  2. Expand the levels or folders to view planned checklists.
  3. Drag bars to adjust dates.
  4. Move entire folders to update all underlying activities.
  5. Adjust individual checklists as needed.


Create dependencies

  1. Select a checklist.
  2. Define a dependency to another checklist.
  3. Use an end-to-start relationship.


Results: data center schedule


Method

Description

Bulk via level

Assigns dates to all checklists under a level

Manual

Sets dates one by one

Excel import

Imports the plan in bulk from a spreadsheet

Gantt drag-and-drop

Visual planning and adjustment


Dependency

Description

End-to-start

A checklist starts when another one finishes

One-to-one

Only one checklist can be linked to another

Level dependency

Entire levels depend on each other (recommended)


Status

Display in Gantt

Approved

Green

Failed

Red

Planned

Default color


Troubleshooting: data center schedule


Problem

Cause

Solution

Dates are not updated correctly

Wrong level or row selected

Select the grey level row for the correct level, then set dates again

Plan changes unintentionally

A folder was moved in Gantt

Undo by editing individual checklists, or move only the intended folder

Plan is too complex

Too many checklist-level dependencies

Prefer level dependencies instead of many one-to-one links

Gantt does not show all data

Levels or folders are collapsed

Expand folders in the Gantt view

Updated on: 07/26/2026