Create a Data Center project in less than 5 minutes
Overview: data center project setup
The asset-based project wizard in CxPlanner lets you create a project, define commissioning levels, add asset types with quantities, attach checklist templates, and assign responsibilities, which is used when starting a structured data center commissioning project.
For spreadsheet bulk import of equipment, see the Excel asset import guides. For Template Center checklist creation, see the Template Center tutorials.
- Your role must be Manager or Admin.
- You can find the menu at Projects - Add Asset-Based Project.
- This changes the project structure, assets, checklists, assignments, and scheduling.
Levels and structure can be adjusted later. Checklists can be reused from templates. Assets can also be imported from a spreadsheet (.xlsx) or PDF after setup.
How to create a data center project
Create the project
- Go to Projects in the sidebar.
- Create an Asset-Based project.
- Enter a project name and choose a project type (for example Data Center).
Define levels
- Select the levels you want (for example Level 1-5).
- Adjust later if needed (for example add Level 3A or 3B).
Add asset types
- Select asset types (for example ATS, PDU, Switchgear).
- Enter the quantity for each type.
- Create the project.
Example quantities: 5 ATS, 10 PDU, 5 server racks, 10 switchboards.
Configure checklists and workflows
- Go to Types: checklists.
- Create or edit checklist types (levels).
- Add additional levels if needed.
- Define dependencies between levels.
- Configure approval workflows (for example Complete, Accept, Approve).
Assign checklists to assets
- Go to Types: Asset.
- Select an asset type (for example ATS).
- Add checklists to each level from the Template Center.
- Repeat for all relevant levels.
- Optionally save the setup as a template for reuse.
Assign checklists in System & Test view
- Go to System & Test view.
- Open a level (for example Level 2) and select the relevant checklists.
- Assign each checklist to a user, a company, or a user group.
- Optionally add start and end dates.
Video guide: data center project setup
Results: data center project setup
- Assets appear in Asset Overview with assigned levels
- Checklists appear as Pending until started
- System & Test view shows a matrix of levels and assets
- Assigned users gain access to their checklists
- Scheduling generates Gantt charts when dates are set
View | Purpose |
|---|---|
Asset Overview | Asset-based overview of equipment |
System & Test view | Test and checklist structure |
Dashboard | Project status and configuration |
Troubleshooting: data center project setup
Problem | Cause | Solution |
|---|---|---|
Checklists not visible on assets | Checklist templates not added to the asset type | Open Types: Asset, select the asset type, and add checklists per level |
Users cannot see checklists | Checklists not assigned to the user, company, or group | Assign them in System & Test view for the relevant level |
Empty levels on assets | No templates attached to those levels | Attach templates to each level under the asset type |
Incorrect project structure | Levels configured incorrectly | Edit levels in project settings and reassign checklists |
Updated on: 07/26/2026