Get a unified timeline across multiple projects with Global Gantt

Overview


How do I view multiple projects in one shared timeline to avoid task overlaps?


The Global Gantt is a timeline module in CxPlanner that lets you group multiple projects into a single, consolidated Gantt view. This makes it easy to spot overlaps, coordinate resources, and plan work

across projects without switching contexts.


Only users with the company role Manager or higher and the project role Viewer or higher can access the Global Gantt.


When and why to use this

Use the Global Gantt when you need a high-level, cross-project overview of timelines and dependencies.

  • When you manage or contribute to multiple projects at the same time
  • When you need to identify overlapping tasks or resource conflicts
  • When you want to align milestones across projects for better planning


What the system does

  • Aggregates tasks from selected projects into one timeline
  • Displays tasks according to their planned dates
  • Keeps each task linked to its original project


Limitations and behaviors

  • Only projects you have access to can be added to the view


How to - step by step

  1. From the home page navigate to Global Gantt
  2. Via the slider add projects that you want to include in the timeline.
  3. Use filters or grouping options to organize the timeline by project, phase, or date range.
  4. Review the combined timeline to identify overlapping tasks or scheduling conflicts.


Step: 1 & 2 - Select you projects


Behavior and results

The Global Gantt provides a synchronized overview without changing the underlying project data.


How tasks are displayed

  • Each task appears based on its planned start and end dates
  • Tasks retain their original project context and permissions
  • Color-coding or labels indicate which project a task belongs to


Troubleshooting

Problem

Cause

Solution

A project does not appear

No access to the project

Ask a project admin for access

Tasks cannot be edited

Global Gantt is read-only

Open the task inside the project

Missing tasks in timeline

Date not defined on task

Add start and end dates to the task

Timeline looks crowded

Too many projects selected

Use filters or remove projects


Quick facts

  • Requires: Company role Manager or higher, Project role Viewer or higher
  • Location: Global Gantt → Project grouping
  • Affects: Timeline overview only (no direct task edits)