Set up a standard commissioning project (PFC + FPT)
Overview
How do I quickly create a commissioning project with assets and checklists in CxPlanner?
This guide explains how to create an asset-based project, define checklist phases, and automatically assign checklists to assets.
When and why to use this
Use this setup when starting a new commissioning project.
Typical use cases:
- Creating assets such as AHUs or exhaust fans
- Setting up pre-functional and functional tests
- Automatically assigning checklists to assets
- Planning and assigning commissioning activities
Key facts:
- Verification phases can be renamed later
- Checklists can be assigned automatically
- Assets and data can be imported later through Excel or PDF
- Planned dates create a timeline automatically
How to - step by step
1. Create the project
- Go to Projects
- Click Add Asset-Based Project
- Enter a project name
- Select a project type
2. Configure checklist phases
- Define your checklist types
- Example: Pre-functional or Functional Performance Test
- Continue to the next step
3. Add asset types
- Add the assets you want in the project
- Example: Air Handling Units or Exhaust Fans
- Define the quantity
- Create the project
4. Assign checklist templates
- Go to Types of Assets
- Select an asset type
- Add checklist templates to the asset
- Repeat for additional checklist types if needed
Example:
Asset Type | Pre-functional | Functional |
|---|---|---|
Air Handling Unit | Yes | Yes |
Exhaust Fan | Yes | No |
5. Review assets and tests
- Open Asset Overview to see all assets
- Open Global Test View to see all checklists
- Assign responsible users, groups, or companies
- Add dates if scheduling is needed
Video guide:
Behavior and results
Feature | Result |
|---|---|
Asset Overview | Shows all project assets |
Global Test View | Shows all checklists |
Checklist Templates | Automatically assign tests |
Timeline | Generated when dates are added |
Bulk Updates | Allows mass editing |
Troubleshooting
Problem | Cause | Solution |
|---|---|---|
Checklists are missing | No template assigned | Add checklist templates to the asset type |
Users cannot see tests | No assignment added | Assign the user or company |
Timeline is empty | No dates added | Add planned dates |
Quick facts
- Requires: Project role Manager or higher
- Location: Projects → Asset-Based Project
- Affects: Assets, checklists, schedules, and reporting