Set up a Timeline and Schedule for Data Centers in the Asset Module

Overview


How do I set up a commissioning or test plan in CxPlanner?


This guide explains how to plan and structure your checklists across levels using dates and the Gantt timeline.


Only users with the project role Manager or higher can plan and edit commissioning plans


When and why to use this

Use this feature when you need to plan and visualize commissioning activities in your project.

  • When you have created assets and assigned checklists
  • When you want to plan test sequences across levels (Level 2-5)
  • When you need to assign start and end dates to checklists
  • When you want to visualize the plan in a Gantt timeline
  • When you need to manage dependencies between activities


Important to know:

  • Planning can be done manually, via bulk updates, or Excel import
  • The Gantt view is based on Microsoft Project logic
  • Changes at folder level affect all underlying checklists
  • Status is displayed visually (green = approved, red = failed)


How to - step by step

Plan checklists directly in the asset view

  1. Go to your project and navigate to Assets
  2. Select an asset (e.g., ATS)
  3. Locate the Start date and End date columns and select a date in the grey row for a level (e.g., Level 3)
  4. The system automatically assigns dates to all underlying checklists


Alternative: Plan one checklist at a time

  1. Click the start date for a specific checklist
  2. Select a date and repeat for the end date


Alternative: Import plan from Excel

  1. Go to Asset Overview and click Options
  2. Select Import and upload your Excel file with dates


Use the Gantt timeline for planning

  1. Go to the menu and select Gantt Timeline
  2. Expand the levels/folders and view planned checklists
  3. Edit the plan directly in the Gantt view
  4. Drag bars to adjust dates
  5. Move entire folders to update all underlying activities
  6. Adjust individual checklists as needed


Create dependencies (Additional)

  1. Select a checklist
  2. Define a dependency to another checklist
  3. Use an end-to-start relationship


Video guide:



Behavior and results


Planning methods

Method

Description

Bulk via level

Assigns dates to all checklists under a level

Manual

Set dates one by one

Excel import

Import plan in bulk

Gantt drag-and-drop

Visual planning and adjustment


Dependencies

Type

Description

End-to-start

A checklist starts when another one finishes

One-to-one

Only one checklist can be linked to another

Level dependency

Entire levels depend on each other (recommended)


Status in Gantt view

Status

Display

Approved

Green

Failed

Red

Planned

Default color


Troubleshooting

Problem

Cause

Solution

Dates are not updated correctly

Wrong level selected

Ensure the correct row is selected

Plan changes unintentionally

Folder was moved

Use individual editing instead

Plan is too complex

Too many dependencies

Use level dependencies instead

Gantt does not show all data

Levels are collapsed

Expand folders in the Gantt view


Quick facts

  • Requires: Manager or higher
  • Location: Assets → Dates / Gantt Timeline
  • Affects: Planning, Gantt view, project status

Updated on: 03/30/2026