Articles on: Asset Module

Commissioning with OPR, BOD (LEED, ASHRAE G0, Std 202)

Overview: commissioning with OPR and BOD


Commissioning with OPR and BOD in the Commissioning tools lets you structure requirements, design responses, reviews, assets, tests, reports, and issues, which is used for projects that follow LEED, ASHRAE Guideline 0, or ASHRAE Standard 202.


  • Your role must be high enough to create projects and change project settings (typically Manager or Admin).
  • You can find the menu at Project Settings - Tools and Modules - Commissioning Block.
  • This enables commissioning tools and changes OPR, BOD, reviews, assets, checklists, reports, and issues for the project.


How to set up commissioning with OPR and BOD


  1. Go to Projects.
  2. Create a new Asset Based Project.
  3. Enter a project name and continue.
  4. Select the project type and checklist types, for example PFC and FPT.
  5. Add the required asset types and quantities.
  6. Open Project Settings.
  7. Go to Tools and Modules.
  8. Enable Commissioning Block.
  9. Go to Commissioning in project settings.
  10. Enable the commissioning tools you need.
  11. Add or import your OPR requirements.
  12. Use BOD to collect designer responses and approve, reject, or postpone them.
  13. Use Reviews to upload drawings or documents and create markup comments.
  14. Attach checklist templates to your asset types.
  15. Enable Reports if you need commissioning reports or final documentation.


Video guide



Results: commissioning tools and workflows


Tool

Purpose

Organization Chart

Project users, groups, interfaces, and communication lines

OPR

Project requirements that must be verified

BOD

Designer or consultant responses to OPR items

Reviews

Document upload, drawing review, markups, and comments

Assets

Project assets and attached checklist structures

Reports

Commissioning documentation combining text, images, and files

Issues

OPR, review, and test-related issues in one log


Step

Result

OPR item is created

Requirement appears in the OPR list

BOD is opened

OPR items are mirrored into BOD

Designer adds a response

Response returns for commissioning review

Commissioning team rejects response

Comment is required and the item returns to the designer

Commissioning team approves response

BOD item is marked approved


Troubleshooting: OPR and BOD commissioning


Problem

Cause

Solution

Commissioning tools are not visible

Commissioning Block is not enabled

Enable Commissioning Block under Project Settings - Tools and Modules

BOD is empty

No OPR items exist yet

Add or import OPR requirements first

Designer cannot approve or reject BOD items

Approval actions belong to the commissioning team

Ask the designer to add or update the BOD response only

Assets do not show checklists

Checklist templates are not attached

Attach templates to the relevant asset types

Reports are not visible

Reports module is not enabled

Enable Reports under Tools and Modules