Overview
How do I set up commissioning with OPR and BOD in CxPlanner?
Commissioning with OPR and BOD in the Commissioning module allows you to structure requirements, design responses, reviews, assets, tests, reports, and issues, which is used for commissioning projects that follow LEED, ASHRAE Guideline 0, or ASHRAE Standard 202.
This guide covers the basic setup and workflow for commissioning with OPR and BOD. It does not cover advanced template setup or detailed reporting configuration.
When and why to use this
Use this setup when your project needs a structured commissioning process with traceable requirements and design verification.
- Use it for commissioning projects that support LEED, BREEAM, ASHRAE Guideline 0, ASHRAE Standard 202, or similar requirements
- Create an asset-based project with test structures such as PFC and FPT
- Manage Owner’s Project Requirements (OPR) as project requirements
- Use Basis of Design (BOD) to collect and review designer responses
- Track review comments, issues, test progress, and reporting in one project
- Enable only the commissioning tools you need for the project
How to - step by step
- Go to Projects.
- Create a new Asset Based Project.
- Enter a project name and continue.
- Select the relevant project type and checklist types, for example PFC and FPT.
- Add the required asset types and quantities.
- Open Project Settings.
- Go to Tools and Modules.
- Enable Commissioning Block.
- Go to Commissioning in the project settings.
- Enable the commissioning tools you need
- Add or import your OPR requirements.
- Use BOD to collect designer responses and approve, reject, or postpone them.
- Use Reviews to upload drawings or documents and create markup comments.
- Attach checklist templates to your asset types.
- Enable Reports if you need commissioning reports or final documentation.
Video guide
Behavior and results
Main commissioning tools
Tool | Purpose |
|---|---|
Organization Chart | Shows project users, groups, interfaces, and communication lines |
OPR | Stores the project requirements that must be verified |
BOD | Collects designer or consultant responses to the OPR requirements |
Reviews | Supports document upload, drawing review, markups, and comments |
Assets | Stores project assets and attached checklist structures |
Reports | Combines text, images, graphics, and files into commissioning documentation |
Issues | Collects OPR, review, and test-related issues in one log |
OPR and BOD workflow
Step | Result |
|---|---|
OPR item is created | The requirement is added to the OPR list |
BOD is opened | OPR items are mirrored into the BOD view |
Designer adds a response | The response is sent back for commissioning review |
Commissioning team rejects response | A comment is required and the item returns to the designer |
Commissioning team approves response | The BOD item is marked as approved |
Review workflow
Action | Result |
|---|---|
Upload documents or drawings | Files are stored in the review area |
Add markup comments | Comments are tracked against the document |
Close comments | Status is updated visually |
Upload new versions | Version history is maintained |
Troubleshooting
Problem | Cause | Solution |
|---|---|---|
Commissioning tools are not visible | Commissioning Block is not enabled | Enable Commissioning Block under Project Settings → Tools and Modules |
BOD is empty | No OPR items have been created | Add or import OPR requirements first |
Designer cannot approve or reject BOD items | Approval actions are for the commissioning team | The designer should only add or update the BOD response |
Assets do not show checklists | Checklist templates are not attached | Attach templates to the relevant asset types |
Reports are not visible | Reports module is not enabled | Enable Reports under Tools and Modules |
Quick facts
- Location: Project Settings → Tools and Modules → Commissioning Block
- Affects: OPR, BOD, reviews, assets, checklists, reports, and issues
Updated on: 05/28/2026