Commissioning with OPR, BOD (LEED, ASHRAE G0, Std 202)
Overview: commissioning with OPR and BOD
Commissioning with OPR and BOD in the Commissioning tools lets you structure requirements, design responses, reviews, assets, tests, reports, and issues, which is used for projects that follow LEED, ASHRAE Guideline 0, or ASHRAE Standard 202.
- Your role must be high enough to create projects and change project settings (typically Manager or Admin).
- You can find the menu at Project Settings - Tools and Modules - Commissioning Block.
- This enables commissioning tools and changes OPR, BOD, reviews, assets, checklists, reports, and issues for the project.
How to set up commissioning with OPR and BOD
- Go to Projects.
- Create a new Asset Based Project.
- Enter a project name and continue.
- Select the project type and checklist types, for example PFC and FPT.
- Add the required asset types and quantities.
- Open Project Settings.
- Go to Tools and Modules.
- Enable Commissioning Block.
- Go to Commissioning in project settings.
- Enable the commissioning tools you need.
- Add or import your OPR requirements.
- Use BOD to collect designer responses and approve, reject, or postpone them.
- Use Reviews to upload drawings or documents and create markup comments.
- Attach checklist templates to your asset types.
- Enable Reports if you need commissioning reports or final documentation.
Video guide
Results: commissioning tools and workflows
Tool | Purpose |
|---|---|
Organization Chart | Project users, groups, interfaces, and communication lines |
OPR | Project requirements that must be verified |
BOD | Designer or consultant responses to OPR items |
Reviews | Document upload, drawing review, markups, and comments |
Assets | Project assets and attached checklist structures |
Reports | Commissioning documentation combining text, images, and files |
Issues | OPR, review, and test-related issues in one log |
Step | Result |
|---|---|
OPR item is created | Requirement appears in the OPR list |
BOD is opened | OPR items are mirrored into BOD |
Designer adds a response | Response returns for commissioning review |
Commissioning team rejects response | Comment is required and the item returns to the designer |
Commissioning team approves response | BOD item is marked approved |
Troubleshooting: OPR and BOD commissioning
Problem | Cause | Solution |
|---|---|---|
Commissioning tools are not visible | Commissioning Block is not enabled | Enable Commissioning Block under Project Settings - Tools and Modules |
BOD is empty | No OPR items exist yet | Add or import OPR requirements first |
Designer cannot approve or reject BOD items | Approval actions belong to the commissioning team | Ask the designer to add or update the BOD response only |
Assets do not show checklists | Checklist templates are not attached | Attach templates to the relevant asset types |
Reports are not visible | Reports module is not enabled | Enable Reports under Tools and Modules |
Updated on: 07/26/2026