Articles on: Tasks / Issues

Import Tasks from Excel

Overview: import tasks from Excel


Excel task import uploads a spreadsheet of tasks into a project, which is used when migrating a punch list or issue list from another tool or a previous project.


For add versus update options and template download, see Import tasks from XLSX.


  • Your role must be project Admin.
  • You can find the menu at Project settings - Advanced - Import tasks.
  • This adds tasks to the project task list. Existing tasks are not overwritten unless they match specific identifiers.


Only users with the project role Admin can perform this action.


How to import tasks from Excel


  1. Go to Project settings in the project.
  2. Select the Advanced tab.
  3. Click Import tasks.
  4. Upload your Excel file containing the tasks.



Results: import tasks from Excel


  • Imported tasks appear in the project task list
  • You can edit, assign, or update them like manually created tasks
  • Incorrectly formatted rows are skipped


Role type

Required role level

Company role

User or higher

Project role

Admin


Troubleshooting: import tasks from Excel


Problem

Cause

Solution

Import option not visible

Project role is below Admin

Ask a project Admin to run the import or raise your role

Some tasks missing after import

Incorrect Excel format or empty rows

Check the file against the CxPlanner format and re-import

File upload fails

File type is not supported

Save the spreadsheet as .xlsx and upload again

Updated on: 07/26/2026

Was this article helpful?

Share your feedback

Cancel

Thank you!